(1) Check whether the spindle cooling system is running normally.
(2) Check whether the main axis is running normally and whether there is an abnormality.
(3) View whether each coordinate axis on the machine tool is running normally, whether there are abnormal sounds, and whether the vibration is too large.
(4) Whether the pressure of the thick hydraulic system is normal (generally 3MPa), whether the installation of the processing parts is correct and reliable.
(5) Check whether the external power supply system is good. If it is abnormal, it must be stopped and cannot be booted forcibly to avoid damaging the machine.
(6) View whether the liquid level of the thickened coolant is normal, whether there is water leakage, and the insufficient time should be added in time. If the quality should be replaced in time.
(7) Check whether the oil level of the lubricating system's oil storage tank is normal. Observe the oil marking line. Turn on the lubricating opening during daily processing, about 2-3 hours, lubricating the screw and guide rail.